Fleet charging project timeline: how long to energisation
Longer than the construction, because the schedule is set by your utility rather than by your electrical contractor. The contractor's scope — trench, conduit, pedestals, terminations — is typically a matter of weeks. The utility's scope — capacity study, make-ready approval, transformer procurement, interconnection and meter set — runs in months, and occasionally in years where new distribution infrastructure is needed. Every published timeline that says a depot takes eight weeks is measuring from the moment the utility work is already done.
Updated 2026-08-20

Why we do not publish a month count
A confident number here would be a made-up number, and a schedule built on a made-up number is worse than no schedule at all.What is stable is the sequence, the dependencies and which phase controls the others. That is what the table below gives you, and it is enough to build a real schedule once you have three dated answers from your utility: capacity study turnaround, make-ready review cycle, and transformer lead time.Ask for those three in writing at first contact. They are the only inputs that turn this shape into dates.
The phases, and what controls each one
Effort spent accelerating a phase that is not on the critical path is usually wasted. Effort spent removing a week from the utility path is worth several times as much.
The one item that cannot start late
Start it before you have selected hardware, before the design is drawn, and before the port count is final. The load letter can carry a range and a stated managed maximum. A utility that hears from you early enough to put the project into its planning cycle is a different utility from one that hears from you when the contractor is mobilised.It is also the conversation that reorders everything else. The answers about existing capacity, the cost of a new service and the transformer lead time will change your port count, your voltage, possibly your site and certainly your dates. Making those decisions before the utility answers means making them twice.Ask in the same conversation which rate schedule applies and whether an EV-specific commercial schedule exists. That is an operating-cost question with a long tail, and the account representative is the person who knows.
What genuinely runs in parallel
Design to the basis the study is likely to confirm, and hold loosely the parts most likely to change. Redrawing after a capacity answer is normal; redrawing three times because the design was frozen too early is not.The permit set can be submitted while equipment is on order, and in most jurisdictions the review is not the constraint.There is no reason for pedestals to sit in a yard for four months, and a good reason not to: warranty clocks and firmware support windows sometimes start at shipment.The make-ready application runs against design, but only so far. Most programs need a design package to review, so the application cannot precede the design entirely — and construction generally cannot precede the approval. That ordering constraint is the one that catches projects out.What does not run in parallel is the transformer. It is a long-lead item on someone else's factory queue, and nothing you do on site shortens it.
Why the timelines you have been quoted are shorter
Measured that way, a depot really is a few weeks of work, and the number is not dishonest. It is answering a different question.The question a fleet operator is asking is when vehicles can charge. That clock starts at the first conversation with the utility and includes every phase in the table above.The gap between those two clocks is where fleet electrification programs fail. Vehicles get ordered against the construction timeline, arrive against the utility timeline, and sit in a yard with nowhere to plug in.So sequence it the other way: order vehicles against the energisation date the utility gives you, with contingency, and treat the construction schedule as the short pole it is.
Where the schedule actually slips
Make-ready approval arriving after construction started. Many programs disqualify work begun before the pre-approval date, which turns a scheduling shortcut into a lost incentive.An incomplete first submittal to the utility. A load letter missing the vehicle schedule, the port count or the in-service date goes to the back of a queue you have already waited in.Redesign after the capacity study. If the study says the existing service cannot carry the design, the design changes and the permit set changes with it.Correction rounds at inspection — usually short, occasionally not, and much more likely where the adopted code edition differs from the one the design assumed. Confirm the adopted edition with the authority having jurisdiction before the drawings are stamped.The compression levers, in order of usefulness: start the utility conversation first, get the transformer lead time in writing before design freeze, submit a complete make-ready application before any construction begins, and build the underground work for the full plan while the trench is open so there is no second project to schedule.
How long does it take to build a fleet charging depot?
The construction is usually weeks. Getting to construction is usually months, because the utility capacity study, the make-ready approval and the transformer all sit on someone else's calendar. Ask your utility for its capacity study turnaround, its make-ready review cycle and the transformer lead time, and build the schedule from those three dates.
What is the critical path on an EV charging project?
The utility path: first contact, capacity study, make-ready approval, transformer procurement, interconnection and meter set. Design, permitting, civil work and installation all have slack against it. Effort spent accelerating the contractor rarely moves the energisation date.
Can I start construction while waiting for the utility?
Physically often yes, contractually often no. Many utility make-ready programs disqualify work started before their pre-approval date, so beginning early can cost you the incentive. Confirm the program's rule in writing before mobilising anything, including trenching.
When should I order the vehicles?
Against the energisation date the utility gives you, with contingency, not against the construction schedule. Vehicles arriving before the depot can charge them is the most common and most expensive sequencing failure in fleet electrification.
Does a Level 2 only depot go faster than one with DC fast charging?
Usually, because it is more likely to fit inside the existing service and avoid new utility infrastructure entirely. A depot that fits the existing service skips the longest phases. That is a real argument for managed Level 2, separate from cost per port.
- US DOE Alternative Fuels Data Center, utility and private incentives — finding the serving utility's charging and make-ready programs, whose review cycles set several phases in the table
- NFPA 70, National Electrical Code, Article 625 — the installation requirements the permit and inspection phases are assessed against; adopted edition varies by jurisdiction
- Recharged, How much does a commercial EV charging station cost — make-ready and electrical infrastructure as the dominant share of commercial charging projects