Skip to the main content
Getting power: utility, make-ready and timelines

What utility make-ready actually covers

Make-ready is the electrical infrastructure that gets power to a charger without being the charger — line extension, transformer, service conductors, switchgear, trenching, conduit and pads. A utility make-ready program pays for some portion of that. Which portion is decided by one thing: where the demarcation point sits between the utility's facilities and your premises wiring. Everything on their side of that point is theirs to build. Everything on yours is your capital, and that is the number your project actually turns on.

Updated 2026-08-20

What utility make-ready actually covers

The demarcation point is the answer everyone skips

The electrical code has a name for it. The service point is the point of connection between the facilities of the serving utility and the premises wiring, and the code's scope explicitly does not cover the utility's own installations on their side of it. Which means the boundary of your electrical project — where your engineer's drawings begin — is defined by the utility, not by the code.Where that point sits is published in your utility's electric service requirements document and reflected in its tariff. On some services it is at the transformer secondary terminals. On others it is at the meter, or at a service pedestal, or at a point on a pole. Those are materially different projects with materially different budgets, and the difference can be the whole secondary run across your yard.So the first question to a utility is not what their make-ready program pays. It is: for a service of this size at this address, where is the service point, and who owns the transformer? Get the answer marked on the one-line diagram. A budget built without that mark is a guess.The second question follows from it: does the make-ready program cover only work on the utility side of that point, or does it extend onto the customer side? That single distinction is usually worth more than the headline incentive amount.

What sits on each side, in practice

Two rows deserve particular attention. Transformer ownership is the single biggest swing item, and it changes both who pays and who carries the lead time risk.And primary trenching on your own property is very commonly split — the customer excavates and backfills to the utility's specification, and the utility installs and terminates the cable inside it.

Three shapes these programs come in

The differences are large. A utility-side-only program can leave the majority of a depot's infrastructure cost with you, because on a large yard the trench, the duct bank and the feeders are the bulk of the work. A customer-side program that reaches the charger stub can change the economics of a whole project.

What make-ready almost never covers

Make-ready means ready for chargers, so the hardware is usually a separate line, a separate incentive if one exists, or simply yours.Permits, plan review and inspection fees are almost always on your side.The network subscription is a per-port annual operating cost, and some programs make it a condition of eligibility rather than something they pay for.If your paving needs resurfacing after the trench, that is generally a civil cost on your side rather than the utility's.And the expensive one: many programs disqualify work commenced before the pre-approval date. Read that clause first, not last.Ongoing operations and maintenance is a real annual number on a depot, and worth budgeting deliberately rather than discovering.

Why this line item is worth the attention

Reported figures put electrical and civil infrastructure at roughly 50 to 70 percent of a commercial charging installation, and at 40 to 60 percent of a DC fast project's total cost.Which means moving the demarcation by fifty feet, or landing inside a program that reaches the customer side, changes the project's capital cost by more than any equipment decision available to you.It also means a per-port price quoted without a named utility is close to meaningless. The same twelve-port depot can carry wildly different net costs in two territories with identical labour rates, purely because one utility's program reaches the charger stub and the other's stops at the transformer.So insist that proposals separate make-ready from hardware, and that the make-ready line states which side of the demarcation each item sits on. A single blended per-port number hides exactly the information you need in order to negotiate.

There is no federal money underneath this

That matters here more than anywhere else in the segment, because it makes utility make-ready the largest recoverable amount most fleet projects will see. What used to be one of two funding sources is now the only one.If a proposal dated after June 30, 2026 carries a federal credit line, treat it as an error to be corrected before signature rather than as an aggressive assumption. A great deal of published material on this subject still has not been revisited.State and local programs may exist alongside the utility layer, and they vary enormously. Neither they nor the utility programs are national, which is why an amount is only useful attached to a named sponsor and a date.

Not yet verifiedThe only quantitative claims on this page are the infrastructure cost shares, attributed to the commercial-secondary sources listed and presented as reported ranges. No make-ready dollar amount is published, because amounts are sponsor-specific and we publish those only against a named utility with a date.

What does utility make-ready cover?

The electrical infrastructure between the grid and the charger: line extension, transformer, metering, and depending on the program, service conductors, switchgear, trenching, conduit and a stub at each charger position. It generally does not cover the chargers themselves, permits, network subscriptions or ongoing maintenance.

What is the difference between utility-side and customer-side make-ready?

The service point divides them. Utility-side work is everything on the utility's side of that connection point — typically line extension, transformer and metering. Customer-side work is everything from there to the charger. Some programs fund only the first; the more generous ones extend across the line, and that difference is usually larger than the headline incentive number.

Where exactly is the demarcation point on my project?

It is defined by your utility in its electric service requirements document, and it varies with service size and configuration — transformer secondary, meter, service pedestal or a point on a pole are all common. Ask for it explicitly and get it marked on the one-line diagram before the budget is set.

Does make-ready pay for the chargers?

Usually not. Make-ready means preparing the site for chargers. Some utilities run a separate hardware rebate, and some turnkey programs supply equipment under a subscription or rate arrangement, but the default assumption should be that the hardware is yours.

Is there a federal make-ready incentive?

No. The Section 30C credit for charging property terminated for property placed in service after June 30, 2026 under Public Law 119-21, including its commercial provision, and nothing federal replaced it. Utility programs, and whatever your state offers, are what remains.

How much of a commercial charging project is make-ready?

Reported figures put electrical and civil infrastructure at roughly 50 to 70 percent of a commercial charging installation, and 40 to 60 percent of a DC fast project's total cost. It is the largest line on most projects, which is why the demarcation question deserves more attention than the charger selection.